Tech Specs

●Shackles are forged alloy steel with alloy pin.
●Size and the Working Load Limit permanently shown on each shackle.
●All shackles with Batch Code which links to Test Certificate and quality traceability.
●100% magnaflux crack detection during manufacturing.
●20,000 cycle fatigue rated to 1.5 times Working Load Limit.
| Item No. |
Nominal Size |
Working Load Limit | Dimensions (inch) | N.W. | |||||||||
| inch | tonnes* | A | B | C | D | E | G | H | K | R | W | lbs | |
|
8-809-26 |
1 | 12.5 | 4.64 | 2.12 | 0.91 | 1.14 | 1.61 | 2.40 | 7.64 | 5.51 | 1.38 | 1.73 | 8.4 |
★ Minimum Ultimate Load is 5 times the Working Load Limit. Maximum Proof Load is 2 times the Working Load Limit.
★ 8-809-19/-26 See Figure 1

Country of Origin
Made in Taiwan